Boeing 737 MAX 7, MAX 10 and 777X: Where Each Stands in October 2026
Key Points
- On August 3, 2026, Boeing announced that the FAA had granted the amended type certificate for the 737-7, clearing the MAX 7 for commercial service.
- AeroTime reported that Boeing disclosed a software issue on September 26, and the Seattle Times reported on October 7 that an FAA review board found no safety risk, though as of October 7 the FAA had not certified the MAX 10.
- In October 2025 Boeing moved first delivery of the 777-9 to 2027 and recorded a pre-tax charge of $4.9 billion on the program.

Boeing has three new airliners that spent years waiting on regulators. The smallest 737 MAX, the MAX 7, cleared that wait in August 2026. The largest, the MAX 10, looked close to clearing it in September, by Boeing's own account, until a software question stopped the clock. The 777X, the company's new long-haul twin, is still in certification flight testing, more than six years after its biggest customer says the first planes were due. This is where each one stands as of October 12, 2026, with every date tied to the person or company that gave it. A plane that is "certified" has its approval in hand. A plane that is "expected" to be certified does not, whoever is doing the expecting.
Why approvals take longer now
The background explains why the regulator has moved slowly on all three. After the 737 MAX's two fatal crashes in late 2018 and early 2019, the FAA and other aviation authorities worldwide grounded the plane, and the FAA did not clear it to fly again until November 18, 2020, as The Points Guy recounted1. Both crashes were tied to a flight control system called MCAS.
Then, in January 2024, a door plug blew out of an Alaska Airlines 737 MAX 9 in flight. The National Transportation Safety Board found that the plug separated because of Boeing's failure to follow proper manufacturing procedures2 (four bolts meant to secure it were missing before the plane was delivered), AVweb reported in July 2025, and it also cited the FAA's "inadequate oversight and audit processes" as contributing factors. The FAA's investigation turned up production and quality lapses across Boeing, and the agency held 737 production to 38 airplanes a month3, a limit it did not ease until October 2025, according to Airways Magazine. The FAA also kept a hand in signing off each new jet. Leeham News reported that Boeing and the FAA had been taking alternating weeks issuing airworthiness certificates for new 737s and 787s, until the FAA fully restored Boeing's authority effective July 20, 20264.
The engine anti-ice problem
The MAX 7 and MAX 10 had their own obstacle, and it had nothing to do with the door plug. The MAX's engine inlets are made of carbon composite rather than metal, and its engine anti-ice system could overheat part of the engine housing. As the Associated Press explained in January 2024, the safety standard involved is "designed to prevent part of the engine housing from overheating and breaking off during flight"5, and broken parts could strike the plane. Regulators told pilots of MAX jets already flying to limit use of the system in dry conditions. Boeing had asked for an exemption so it could deliver the MAX 7 before meeting that standard. On January 29, 2024, it withdrew the request and said it would instead "incorporate an engineering solution that will be completed during the certification process."
That solution took longer than planned. In July 2025 The Air Current reported that Boeing's preferred fix had created another safety issue in testing, and that the unfinished fix had pushed approval of both the MAX 7 and MAX 10 into 20266.
The MAX 7 was certified on August 3, 2026
On August 3, 2026, Boeing announced that the FAA had granted the amended type certificate for the 737-77, Boeing's name for the MAX 7, clearing it for commercial service. AVweb reported that the FAA also required updates to flight control software and cockpit alerts, along with a redesigned engine anti-ice system8. Boeing says the plane seats 135 to 160 passengers in two classes, flies up to 3,800 nautical miles, and is the longest-range member of the MAX family.
Certified does not mean carrying passengers yet. Boeing says its teams have started refurbishment work on MAX 7s built earlier, and the analytics firm Cirium estimated, as AVweb reported, that Boeing had already assembled about 30 of them. Southwest Airlines, the launch customer, told Reuters it expects the plane to enter service in the coming months, though AVweb noted the model was not in Southwest's published schedule through March 2027.
The MAX 10 is not certified yet
The MAX 10 is the largest MAX, seating 185 to 210 passengers with a range of up to 3,100 nautical miles7, according to Boeing. In mid-July 2026 Boeing reported its certification flight testing 98 percent complete9, after about 2,060 flight hours. Its second-quarter results on July 28 said certification flight testing had been completed on both the 737-7 and 737-1010, and that the company continued "to anticipate certification in 2026 and first delivery in 2027 for both variants." On September 16, chief executive Kelly Ortberg said, "I think you're going to see that certification very soon,"11 and that Boeing was "just in the documentation phase."
Ten days later the schedule slipped again. On September 26 Boeing disclosed a software issue in which pilots could lose access to automated flight guidance during a specific landing scenario, AeroTime reported, and on September 28 FAA Administrator Bryan Bedford said, "We will be delaying the 10 until we're satisfied that we don't have an issue here."12 Leeham News reported that the problem involved flight management software installed on certain 737 MAX aircraft, including MAX 10s and MAX 7s13.
The pause was short. The Seattle Times reported on October 7 that the FAA's Corrective Action Review Board found no safety risk, because "pilots retain full control of the aircraft and the indications to the flight crew are clear and unambiguous."14 Aviation Week reported that after the panel's October 2 decision, the FAA will not require Boeing to update the software15 as a condition of certifying the MAX 10. Leeham News wrote on October 6 that certification "appears back on track,"13 and analysts quoted by the Seattle Times said it was likely back on track for this year. As of the latest reporting opened for this article, from October 7, the FAA had not certified the MAX 10.
Who is waiting for the MAX 10
Airlines have ordered about 1,500 MAX 10s, according to Cirium figures cited by Leeham News16 in September, which named Alaska Airlines, American Airlines, Lufthansa Group, WestJet and Vueling among the customers. Ryanair holds one of the largest commitments. In May 2023 the Irish airline placed a firm order for 150 737-10 jets and options for 150 more17, and Boeing said the plane gives Ryanair 228 seats. In the fourth quarter of 2025, Boeing booked 105 737-10s for Alaska Airlines18, and in the first quarter of 2026 it booked 25 for Aviation Capital Group19. Alaska had expected certification by the end of September, and its chief operating officer, Jason Berry, told Reuters on September 24, before the pause, that the airline planned to receive its first MAX 10 in spring 202712, AeroTime reported. United Airlines said it was not accepting deliveries of aircraft carrying the software version under review.
Some of the planes already exist. Cirium counted about a dozen MAX 10 airframes plus three test aircraft16, Leeham News reported, and most MAX 10 production is planned for the new North Line in Everett, Washington.
How fast Boeing can build them
In October 2025 Boeing said it had stabilized 737 production at 38 a month and had "jointly agreed with FAA in October to increase to 42 per month."20 In April 2026 it reported that the program "continues to produce at a 42 per month rate."19 In late May, FlightGlobal reported that the FAA agrees Boeing's production system is ready21 for another rate increase. Boeing's July results said the 737 program began transitioning to 47 a month10 in the second quarter and started low-rate initial production on the 737 North Line in July. Ortberg was careful about it in September: "We're now driving at 47 a month, but we are not stable yet at 47 a month."11
The 777X is years late and still testing
The 777X is Boeing's new widebody family, and the 777-9 passenger model is the one going through certification first. Emirates president Tim Clark said in July 2026, "We should have had the planes in April 2020,"25 as Reuters reported. In January 2021, when Boeing pushed the jet's entry into service to late 2023 and took a $6.5 billion pre-tax charge, Reuters noted that even the previous 2022 target was "already two years later than planned."22 In October 2024, citing delays in flight testing, Boeing said it anticipated first delivery of the 777-9 in 2026 and the 777-8 freighter in 202823. A year later, in October 2025, it moved the 777-9 again, to 2027, and recorded a pre-tax charge of $4.9 billion20 on the program.
Since then the testing has moved through the FAA's stages, called Type Inspection Authorizations. Boeing reported starting the TIA 3 phase18 in the fourth quarter of 2025, FAA approval for TIA 4a19 in the first quarter of 2026, and approval to begin flight testing under TIA 4B10 in the second quarter. In mid-July, Boeing said the test fleet had logged more than 4,800 flight hours and roughly 1,700 flights9, with half of planned certification testing complete and the ETOPS-focused authorizations still to come. Boeing says ETOPS approval will let operators fly the airplane extended distances from suitable airports, and that the testing includes proving flights to show the 777-9 can safely and reliably fly trans-oceanic routes28.
That is where the latest uncertainty sits. On September 16 Ortberg said, "We may see some of the testing spill into next year,"24 because GE Aerospace needs more testing than expected to certify a fix for a durability problem with a seal in the GE9X engine, Air Data News reported. The same day, Boeing said the program "remains on track for first delivery in 2027."11 The FAA said in July that it expected the aircraft to be certified late this year or early next year25, Reuters reported. By October, Leeham News was reporting the 777-9's type certificate as "now expected to come in 2027."13
Who is waiting for the 777X
Emirates has the biggest order of the two airlines here by far. According to ch-aviation in August 2026, it has 235 777-9s and 35 777-8s on order27. Boeing booked 65 777-9s for the airline in the fourth quarter of 202518; the ch-aviation article does not say whether its total includes them. Clark told reporters at the Farnborough Airshow on July 21 that Emirates expects its first 777-9 during the second quarter of 202726, and Reuters reported that he called adding the planes in 2027 "a stretch."
Lufthansa, a launch customer, has 20 777-9s on order, and its chief executive, Carsten Spohr, said that first deliveries were expected in the first quarter of 2027 and that Boeing still targeted entry into service that summer, ch-aviation reported27. Spohr also has a backup plan ready: "If there are further delays, we would reactivate A340-300s, which we have kept for this purpose to cover the network."27
The freighter version, the 777-8F, trails the passenger model. The last firm date for it in the Boeing results releases opened for this article is the October 2024 target of first delivery in 202823. Boeing's later releases opened here do not restate it.
What to watch next
Three milestones will settle most of this. The first is the MAX 10's amended type certificate, which Boeing has said it expects in 2026 and which the FAA's October 2 finding cleared of its most recent obstacle. The second is the first MAX 7 and MAX 10 deliveries, which Boeing has said will begin in 2027. The third is the start of ETOPS testing on the 777-9, which Air Data News reported24 was waiting on a GE9X seal fix. Ortberg said some of the 777-9's testing could spill into next year. Spohr has said Boeing's first deliveries are expected in the first quarter of 2027, and Emirates expects its first 777-9 in the second quarter.
Sources
- Zach Griff, United Airlines' 737 MAX return to service, The Points Guy, February 11, 2021. Accessed October 12, 2026.
- Amelia Walsh, NTSB Cites Boeing, FAA Shortcomings In Alaska Door Plug Final Report, AVweb, July 10, 2025. Accessed October 12, 2026.
- Lorne Philpot, FAA Lifts Boeing 737 MAX Production Cap, Airways Magazine, October 19, 2025. Accessed October 12, 2026.
- Howard Hardee, Boeing secures FAA approval to issue airworthiness certificates for new 737s and 787s, Leeham News, July 17, 2026. Accessed October 12, 2026.
- Gene Johnson, Boeing withdraws request for safety exemption due to issue that could cause engine housing to break off, Associated Press via NBC4 Washington, January 29, 2024. Accessed October 12, 2026.
- Jon Ostrower, Unresolved engine anti-ice fix pushes 737 Max 7 and 10 certifications into 2026, The Air Current, July 24, 2025. Accessed October 12, 2026.
- FAA certifies 737-7, Boeing, August 3, 2026. Accessed October 12, 2026.
- Matt Ryan, FAA Certifies Boeing 737 MAX 7, AVweb, August 4, 2026. Accessed October 12, 2026.
- Certification progress reported on 737 MAX models, 777-9, Boeing, July 16, 2026. Accessed October 12, 2026.
- The Boeing Company, Boeing Reports Second-Quarter Results (Exhibit 99.1 to Form 8-K, SEC), July 28, 2026. Accessed October 12, 2026.
- CEO: 737-10 certification very soon, more to do to stabilize production, Boeing, September 16, 2026. Accessed October 12, 2026.
- Stephen Pope, FAA delays Boeing 737 MAX 10 certification over software, AeroTime, September 28, 2026. Accessed October 12, 2026.
- Howard Hardee, Boeing's Path to Max 10 Certification Looks Clear Again, Leeham News, October 6, 2026. Accessed October 12, 2026.
- Lauren Rosenblatt, Boeing 737 Max software glitch not a safety risk, FAA says, The Seattle Times via Aviation Pros, October 7, 2026. Accessed October 12, 2026.
- Sean Broderick, FAA Says Software Issue Will Not Stop Boeing 737-10 Certification, Aviation Week, October 3, 2026. Accessed October 12, 2026.
- Howard Hardee, Boeing Suffers Another Delay Painfully Close to 737 Max 10 Certification, Leeham News, September 28, 2026. Accessed October 12, 2026.
- Ryanair Places Its Biggest Boeing Order for up to 300 737 MAX Jets, Boeing, May 9, 2023. Accessed October 12, 2026.
- The Boeing Company, Boeing Reports Fourth-Quarter Results (Exhibit 99.1 to Form 8-K, SEC), January 27, 2026. Accessed October 12, 2026.
- The Boeing Company, Boeing Reports First-Quarter Results (Exhibit 99.1 to Form 8-K, SEC), April 22, 2026. Accessed October 12, 2026.
- The Boeing Company, Boeing Reports Third-Quarter Results (Exhibit 99.1 to Form 8-K, SEC), October 29, 2025. Accessed October 12, 2026.
- Jon Hemmerdinger, Boeing starts running 737 production system at 47 monthly rate, FlightGlobal, May 28, 2026. Accessed October 12, 2026.
- Boeing posts record annual loss and again delays new 777X jet, Reuters via Al Jazeera, January 27, 2021. Accessed October 12, 2026.
- The Boeing Company, preliminary third-quarter 2024 results (Exhibit 99.1 to Form 8-K, SEC), October 11, 2024. Accessed October 12, 2026.
- Ricardo Meier, Boeing says 777-9 testing could extend into 2027 over GE9X issue, Air Data News, September 17, 2026. Accessed October 12, 2026.
- Joanna Plucinska and David Shepardson, Emirates expects Boeing 777-9 deliveries in second quarter 2027, president says, Reuters via Zawya, July 21, 2026. Accessed October 12, 2026.
- Fiona Craig, Emirates targets second quarter 2027 delivery for Boeing 777-9 as certification nears, Finviz, July 21, 2026. Accessed October 12, 2026.
- Hilka Birns, Lufthansa touts Boeing compensation on early B777X units, ch-aviation, August 13, 2026. Accessed October 12, 2026.
- Seventh 777-9 completes first flight, Boeing, July 29, 2026. Accessed October 12, 2026.